CLAUSE
|
RED
BOOK
|
YELLOW
BOOK
|
GREEN
BOOK
|
SILVER
BOOK
|
The
Employer
|
||||
Right of access to the site
|
Employer shall give right of access to
the contractor at time mentioned in appandix or time require contractor
commence the work according to programme
Contractor can claim for time and cost
if right of access delayed by contractor
|
Same as red
|
Employer shall give right of access to
the contractor at time mentioned in appendix
Other detail not available
(Provision of site)
|
Same as red
|
Permits, Licences or Approvals
|
Employer shall give an asisstent to
contractor obtain any Permits, Licences or Approvals by low of country by
request of contractor(there are 3 specified type of approvals)
|
Same as red
|
Same as red but there are no specified
areas
|
Same as red
|
Employer's Personnel
|
The employer shall responsible for
employer’s personal and employer’s contractor on site and they shall
coordinate with contractors work
|
Same as red
|
Not available
|
Same as red
|
Employer’s Financial Arrangements
|
Employer shall submit by request from
contractor, evidence that financial arrangement have been made
|
Same as red
|
Not available
|
Same as red
|
Employer’s Claims
|
Employer can claim time and money if
he entitle under any clause of condition or under a contract
The claim amount can be deductible
from contractor’s payments
|
Same as red
|
Not available
|
Same as red
|
The
Engineer
|
||||
Engineer’s Duties and Authorities
|
Employer shall appoint an Engineer or
representative to act on behalf of him by giving some authority.
Engineer shall act according authority
delegated through the contract
Engineer has no authority to relieve
any party from responsibilities
|
Same as red
|
Engineer has full authority which
client has, except termination of contract
|
Same as red
|
Delegation by the Engineer
|
Engineer can assign duties and
delegate authorities to the assistant
The assignment or dedication shall
informed to both parties in written
Assistant shall act according to the
given delegation
Any act of delegated person shall have
same effect as Engineer
|
Same as red
|
Not available
|
Same as red
|
Replacement of the Engineer
|
Employer can replace the Engineer by
giving prior notice to the contractor not less than 42 days
|
Same as red
|
Not available
|
Employer can replace the Engineer by
giving prior notice to the contractor not less than 14 days
|
Instructions of the Engineer or Instruction
|
Engineer or Engineer’s representative
shall issue instructions which necessary to execute the work
If any instruction constitute a
variation, variation clause shall apply
|
Employer shall issue instructions
which necessary to execute the work
If any instruction constitute a
variation, variation clause shall apply
|
||
Determinations
|
Engineer shall make fair determination
to any issue to reach agreement between parties
If parties dissatisfy can go for claim,
Dispute and Arbitration
|
Same as red
|
Not available
|
Same as red
Contractor shall give notice of
dissatisfaction within 14 days after determination
|
Nominated Subcontractors
|
Employer can nominate own
sub-contractor
Contractor shall raise reasonable
objection to employ a sub-contractor by
notice to the Engineer
Payment shall be made by contractor
after certified by the engineer
|
Same as red
but no payment instructions
|
Not available
|
Same as red
but no payment instructions
|
Staff
and Labour
|
||||
Engagement of Staff and Labour
|
Contractor shall make
arrangements for the engagement of all
staff and labour
|
Same
as red
|
Not
available
|
Same
as red
|
Rates of Wages and Conditions of
Labour
|
Contractor shall pay rates of wages
and obsereve conditions of labour not lower than the established for trade or
general level
|
Same
as red
|
Not
available
|
Same
as red
|
Persons in the Service of Employer
|
Contractor shall not recruit, staff or
labour from Employer’s personals
|
Same
as red
|
Not
available
|
Same
as red
|
Labour Laws
|
Contractor shall comply with all
relevant labour laws applicable to employer’s personals and his employees
|
Same
as red
|
Not
available
|
Same
as red
|
Working Hours
|
No work shall carried out during
recognized holidays and except working time mentioned in appendix without
proper reason
|
Same
as red
|
Not
available
|
Same
as red
|
Facilities for Staff and Labour
|
Contractor shall provide and maintain
all accommodation and welfre facilities for his personals and for employer’s
personal according to specification
Can’t provide accommodation for
contractor’s personal within constructiong building
|
Same
as red
|
Not
available
|
Same
as red
|
Health and Safety
|
Contractor shall make reasonable
precution to maintain the health and safety of contractor’s and employer’s
personals.
|
Same
as red
|
Not
available
|
Same
as red
|
Contractor’s Superintendence
|
Contractor shall provide all
necessary superintendence for the
satisfactory and safe execution of the Works
|
Same
as red
|
Not
available
|
Same
as red
|
Contractor's Personnel
|
Contractor can have personals on site
but Engineer may require the Contractor to remove any person due to proper
reason
|
Same
as red
|
Not
available
|
Same
as red
|
Records of Contractor's Personnel and
Equipment
|
Contractor shall submit, to the
Engineer, details showing the Contractor’s Personnel and equipment monthly
|
Same
as red
|
Not
available
|
Same
as red
|
Disorderly Conduct
|
Contractor shall take all reasonable
precautions to prevent any
disorderly conduct by or amongst the
Contractor's Personnel
|
Same
as red
|
Not
available
|
Same
as red
|
Plant,
Materials and Workmanship
|
||||
Manner of Execution
|
Contractor shall execute any work
accordance with manner specified or with recognized practice.
|
Same
as red
|
Not
available
|
Same
as red
|
Samples
|
Contractor shall submit relevant
sample with adequate information to the Engineer
|
Same
as red
|
Not
available
|
Same
as red
|
Inspection
|
Employer’s personal shall have accsess
to any part site at any time to conduct inspection or test and similar act
Contractor shall give full opportunity
to carry out these works
|
Same
as red
|
Not
available
|
Same
as red
|
Testing
|
Contractor shall provide all necessary
assistance and resouses require to carry out th specified tes efficientlyi
Cost of additional test due to
contractor’s matter, have to bear by contractor
|
Same
as red
|
Not
available
|
Same
as red
|
Rejection
|
Engineer may reject any material,
design and workmenship if it found to be defective or not in accordance with
contract with reason by test or inspection
Employer can claim for additional cost
of retesting due to rejection
|
Same
as red
|
Not
available
|
Same
as red
|
Remedial Work
|
Engineer may instruct the
Contractor to do any remedial work in
some situations
If contractor fail to do employer can
appoint other person to carry out the work and entitle to employer’s claim
|
Same
as red
|
Not
available
|
Same
as red
|
Ownership of Plant and Materials
|
Except these two situation, employer
will be the owner for plant and materials
(a) When
it is delivered to site
(b) When
contractor is entitle to payment for plant and material according to clause
8.10
|
Same
as red
|
Not
available
|
Same
as red
|
Royalties
|
Same
as red
|
Not
available
|
Same
as red
|