FIDIC 1999- Clause Comparison- 1 - Quantity Surveying Practices

Thursday, July 12, 2012

FIDIC 1999- Clause Comparison- 1

 





CLAUSE
RED BOOK
YELLOW BOOK
GREEN BOOK
SILVER BOOK
The Employer




Right of access to the site
Employer shall give right of access to the contractor at time mentioned in appandix or time require contractor commence the work according to programme
Contractor can claim for time and cost if right of access delayed by contractor
Same as red
Employer shall give right of access to the contractor at time mentioned in appendix
Other detail not available
(Provision of site)
Same as red
Permits, Licences or Approvals
Employer shall give an asisstent to contractor obtain any Permits, Licences or Approvals by low of country by request of contractor(there are 3 specified type of approvals)
Same as red
Same as red but there are no specified areas
Same as red
Employer's Personnel
The employer shall responsible for employer’s personal and employer’s contractor on site and they shall coordinate with contractors work
Same as red
Not available
Same as red
Employer’s Financial Arrangements
Employer shall submit by request from contractor, evidence that financial arrangement have been made
Same as red
Not available
Same as red
Employer’s Claims
Employer can claim time and money if he entitle under any clause of condition or under a contract
The claim amount can be deductible from contractor’s payments
 Same as red
Not available
Same as red
The Engineer




Engineer’s Duties and Authorities
Employer shall appoint an Engineer or representative to act on behalf of him by giving some authority.
Engineer shall act according authority delegated through the contract
Engineer has no authority to relieve any party from responsibilities

Same as red
Engineer has full authority which client has, except termination of contract
Same as red
Delegation by the Engineer
Engineer can assign duties and delegate authorities to the assistant
The assignment or dedication shall informed to both parties in written
Assistant shall act according to the given delegation
Any act of delegated person shall have same effect as Engineer
Same as red
Not available
Same as red
Replacement of the Engineer
Employer can replace the Engineer by giving prior notice to the contractor not less than 42 days
Same as red
Not available
Employer can replace the Engineer by giving prior notice to the contractor not less than 14 days
Instructions of the Engineer or Instruction
Engineer or Engineer’s representative shall issue instructions which necessary to execute the work
If any instruction constitute a variation, variation clause shall apply


Employer shall issue instructions which necessary to execute the work
If any instruction constitute a variation, variation clause shall apply
Determinations
Engineer shall make fair determination to any issue to reach agreement between parties
If parties dissatisfy can go for claim, Dispute and Arbitration
Same as red
Not available
Same as red
Contractor shall give notice of dissatisfaction within 14 days after determination
Nominated Subcontractors
Employer can nominate own sub-contractor
Contractor shall raise reasonable objection to employ a sub-contractor  by notice to the Engineer
Payment shall be made by contractor after certified by the engineer
Same as red
but no payment instructions
Not available
Same as red
but no payment instructions
Staff and Labour




Engagement of Staff and Labour
Contractor shall make
arrangements for the engagement of all staff and labour
Same as red
Not available
Same as red
Rates of Wages and Conditions of Labour
Contractor shall pay rates of wages and obsereve conditions of labour not lower than the established for trade or general level
Same as red
Not available
Same as red
Persons in the Service of Employer
Contractor shall not recruit, staff or labour from Employer’s personals
Same as red
Not available
Same as red
Labour Laws
Contractor shall comply with all relevant labour laws applicable to employer’s personals and his employees
Same as red
Not available
Same as red
Working Hours
No work shall carried out during recognized holidays and except working time mentioned in appendix without proper reason
Same as red
Not available
Same as red
Facilities for Staff and Labour
Contractor shall provide and maintain all accommodation and welfre facilities for his personals and for employer’s personal according to specification
Can’t provide accommodation for contractor’s personal within constructiong building
Same as red
Not available
Same as red
Health and Safety
Contractor shall make reasonable precution to maintain the health and safety of contractor’s and employer’s personals.
Same as red
Not available
Same as red
Contractor’s Superintendence
Contractor shall provide all
necessary superintendence for the satisfactory and safe execution of the Works
Same as red
Not available
Same as red
Contractor's Personnel
Contractor can have personals on site but Engineer may require the Contractor to remove any person due to proper reason
Same as red
Not available
Same as red
Records of Contractor's Personnel and Equipment
Contractor shall submit, to the Engineer, details showing the Contractor’s Personnel and equipment monthly
Same as red
Not available
Same as red
Disorderly Conduct
Contractor shall take all reasonable precautions to prevent any
disorderly conduct by or amongst the Contractor's Personnel
Same as red
Not available
Same as red
Plant, Materials and Workmanship




Manner of Execution
Contractor shall execute any work accordance with manner specified or with recognized practice.
Same as red
Not available
Same as red
Samples
Contractor shall submit relevant sample with adequate information to the Engineer
Same as red
Not available
Same as red
Inspection
Employer’s personal shall have accsess to any part site at any time to conduct inspection or test and similar act
Contractor shall give full opportunity to carry out these works
Same as red
Not available
Same as red
Testing
Contractor shall provide all necessary assistance and resouses require to carry out th specified tes efficientlyi
Cost of additional test due to contractor’s matter, have to bear by contractor
Same as red
Not available
Same as red
Rejection
Engineer may reject any material, design and workmenship if it found to be defective or not in accordance with contract with reason by test or inspection
Employer can claim for additional cost of retesting due to rejection
Same as red
Not available
Same as red
Remedial Work
Engineer may instruct the
Contractor to do any remedial work in some situations
If contractor fail to do employer can appoint other person to carry out the work and entitle to employer’s claim
Same as red
Not available
Same as red
Ownership of Plant and Materials
Except these two situation, employer will be the owner for plant and materials
(a)    When it is delivered to site
(b)   When contractor is entitle to payment for plant and material according to clause 8.10
Same as red
Not available
Same as red
Royalties

Same as red
Not available
Same as red

No comments: