According to fidic 1999, variations are either initiated the
Engineer or contractor is instructed to submit a proposal. It would be a change
in quantity, quality, levels or dimensions, omission of any work, any
additional work or change in timing and sequence of the works.
Amendment to the Contract is change in conditions of
contract, adding new conditions and etc with a supplementary agreement. This
amendment shall only be born by either contractor or employer with the approval
of other party. Engineer has no right to amend the contract for any reason.