Can Contractor reject the variation order? - Quantity Surveying Practices

Friday, January 8, 2016

Can Contractor reject the variation order?

What is the variation ?

Yeah. Contractor can reject the variation orders given by Engineer.

But this situation shall be managed based on the contract agreement between Employer and the Contractor.
For example if the project contract is based on FIDIC 1987, instructions to variations can be given only by the Engineer under the clause 51.1. The instructions given shall be necessary and appropriate. therefore in case if the instructions to variations are not necessary and