TOWER CRANE
ü A concrete pad is constructed using grade 50 concrete and with steel bars greater than T16.
ü The base is bolted to the ground.
ü Size of the concrete pad depends on the maximum height of the tower crane and the maximum load it may carry.
ü The long horizontal arm is called as working arm, which is the portion of the crane that carries the load. A trolley runs along that arm to move the load in and out from the crane's center.
ü The shorter horizontal arm is called as machinery arm, which contains the crane's motors and electronics as well as the large concrete counter weights.
ü Tower crane units are delivered to site using a long trailer.
ü Initially, tower units, boom and other equipments are assembled using a mobile crane.
ü Later when building goes up, tower crane also move up itself using hydraulic jacking system.
Jacking system
Hydraulic lifting unit lifts the rotation unit 2m above together with the arm. (arm is fixed to rotation unit). Then there will be a 2m gap between top of the last tower unit and the rotation unit. Then the tower crane itself lifts one tower unit at once and assemble it using nuts and bolt between the created gap. Later rotation unit again fixed to the top of the new tower unit.
ü This method is revised to remove the tower units after completion
ü To remove the large concrete pad (if necessary), first drill few holes in it and then add a special chemical to crack it easily.
PRICING OF TOWER CRANE FOR A 10 STOREY BUILDING |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
Preparation of the concerete base |
| ||||||||||||||
| |||||||||||||||
Assumption |
| ||||||||||||||
the size of the concrete base is 4 x 4 x 2.5 m3 sized made of grade 50 concrete. |
| ||||||||||||||
the thickness of the lean concrete layer is 75 mm with grade 15 concrete. |
| ||||||||||||||
excavated materials keep by the pit. |
| ||||||||||||||
| |||||||||||||||
excavation of pit to install the concrete base. |
| ||||||||||||||
| |||||||||||||||
Excavator | 6 | hr | @ | 2000.00 | 12000 |
| |||||||||
uk labour | 9 | hr | @ | 80.00 | 720 |
| |||||||||
12720.00 |
| ||||||||||||||
| |||||||||||||||
Materials for the concrete base |
| ||||||||||||||
| |||||||||||||||
Total area of f/w to be provided | = (4x 4) x 2 x 2.5 |
| |||||||||||||
= 40 m2 |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
Volume of lean concrete | = 4 x 4 x 0.075 |
| |||||||||||||
= 1.2 m3 |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
Volume of grade 50 concrete | = 4 x 4 x 2.5 |
| |||||||||||||
= 40 m3 |
| ||||||||||||||
| |||||||||||||||
Assumption |
| ||||||||||||||
150 kg of 16 mm high yield steel bars are included in 1m3 of concrete |
| ||||||||||||||
| |||||||||||||||
Total weight of 16mm dia r/f | = 150 x 40 |
| |||||||||||||
= 6000 kg |
| ||||||||||||||
= 6 T |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Cost of materials |
| ||||||||||||||
| |||||||||||||||
F/w | 40 | m2 | @ | 800.00 | 32000 |
| |||||||||
Lean concrete | 1.2 | m3 | @ | 12500.00 | 15000 |
| |||||||||
Grade 50 concrete | 40 | m3 | @ | 14500.00 | 580000 |
| |||||||||
R/f | 6 | T | @ | 125000.00 | 750000 |
| |||||||||
1377000.00 |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
Cost for curing and other related item of construction of base slab | 10000.00 |
| |||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Tower Crane |
| ||||||||||||||
| |||||||||||||||
the height of the floor of the building | 3.5m |
| |||||||||||||
Total height of the building | 35m |
| |||||||||||||
the maximum height of the tower crane | 45m |
| |||||||||||||
| |||||||||||||||
| |||||||||||||||
Tower crane hiring |
| ||||||||||||||
| |||||||||||||||
Assumption |
| ||||||||||||||
Tower crane is hired from a company for monthly payment basis |
| ||||||||||||||
monthly cost for the tower crane is Rs 200000 |
| ||||||||||||||
Expected hiring duration | 12 month |
| |||||||||||||
Hiring cost of the tower crane | 12 months | @ | 200000.00 | 2400000.00 | |||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Tower Crane transportation cost |
| ||||||||||||||
| |||||||||||||||
Assumption |
| ||||||||||||||
It need 8 trips of law bed truck to bring complete tower crane to the site |
| ||||||||||||||
Single complete trip of the truck takes 9 hours |
| ||||||||||||||
JCB takes 16 hrs to loading and 16 hrs to unloading |
| ||||||||||||||
time taken to transport the complete tower crane | 72 | hours |
| ||||||||||||
Cost to transport back to the supplier after 1 yr is same as the cost of transport to |
| ||||||||||||||
the site plus the relevant price escalation |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
transport cost | 72 | hrs | @ | 1200.00 | 86400 |
| |||||||||
loading & unloading | 32 | hrs | @ | 2000.00 | 64000 |
| |||||||||
uk labour | 70 | hrs | @ | 80.00 | 5600 |
| |||||||||
cost of transport | 156000.00 |
| |||||||||||||
| |||||||||||||||
cost for transport | 156000 |
| |||||||||||||
Additional cost due to escalation | 7800 |
| |||||||||||||
cost of transport back | 163800.00 |
| |||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Tower crane erection |
| ||||||||||||||
| |||||||||||||||
Assumption |
| ||||||||||||||
Cost of dismantling is same as the cost of erection plus the additional cost for |
| ||||||||||||||
price escalation |
| ||||||||||||||
It is required to hire a mobile crane for 20 hours for the rate of 3500 per hour |
| ||||||||||||||
| |||||||||||||||
mobile crane | 35 | hrs | @ | 3500.00 | 122500 |
| |||||||||
sk labour | 80 | hrs | @ | 120.00 | 9600 |
| |||||||||
uk labour | 50 | hrs | @ | 80.00 | 4000 |
| |||||||||
tools | 1360 |
| |||||||||||||
cost of erection | 137460.00 |
| |||||||||||||
| |||||||||||||||
Cost of dismantling |
| ||||||||||||||
| |||||||||||||||
cost of erection | 137460 |
| |||||||||||||
Additional cost due to escalation | 6873 |
| |||||||||||||
cost of dismantling | 144333.00 |
| |||||||||||||
| |||||||||||||||
Demolition of concrete base |
| ||||||||||||||
| |||||||||||||||
drilling the base | 7000 |
| |||||||||||||
chemical to weaken the concrete | 20 | lit | @ | 750.00 | 15000 |
| |||||||||
breaking the concrete | 30000 |
| |||||||||||||
disposal of materials | 45000 |
| |||||||||||||
97000.00 |
| ||||||||||||||
Total cost to hire, transport and erection & dismantling of the crane | 4,498,313.00 |
| |||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Operational Cost |
| ||||||||||||||
| |||||||||||||||
Assumptions |
| ||||||||||||||
the expected operational duration of the tower crane is 1000 hours |
| ||||||||||||||
| |||||||||||||||
Consider for the complete duration |
| ||||||||||||||
| |||||||||||||||
Operator | 11.5 | mth | @ | 45000.00 | 517500 |
| |||||||||
Helper | 11.5 | mth | @ | 25000.00 | 287500 |
| |||||||||
Generator | 1000 | hrs | @ | 200.00 | 200000 |
| |||||||||
Diesel | 15000 | lit | @ | 75.00 | 1125000 |
| |||||||||
| |||||||||||||||
Total operational cost | 2,130,000.00 |
| |||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
Total cost related to the tower crane | 6,628,313.00 |
| |||||||||||||
| |||||||||||||||
Number of operating hours | 1000 hrs |
| |||||||||||||
| |||||||||||||||
Hourly cost of tower crane | Rs | 6628.31 |
| ||||||||||||
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
No comments: